construction of the 220/110kv praga station with the introduction of 220kv mi硂sna-mory line, poland
the project was signed in november 2017. it includes construction of a new 110/220kv substation, including 16 nos. 220kv gis bays and 30 nos. 110kv gis bays, construction of 4.3 km 220kv cable line.