reconstruction of the 400 kv switchgear and construction of the 110 kv bay in the 400/220/110 kv kozienice substation, poland
the substation is finished in june 2018. the project includes dismantling the existing 9 nos. 400kv switchgear bays, rebuilding 24 nos. 400kv switchgear bays with secondary equipment, extension 1 no. 110kv switchgear bays, and dismantling 5 km transmission line. the substation could not be power out completely during constructing, which increase